Thursday, 29 March 2018


Balancing of machines for complete process house :Part-5 Dyeing

For this purpose one CDR (Continuous Dyeing Range - Open width) is required

Machine working speed: 40 m/min, M/c utilization= 75%

Total production per shift (8 hours or 480 min)= (speed x utilization x 480)/100
= (40 x 75 x 480)/100 = 14,400 meter

Total fabric to be dyed= 50,000/-

14,400 meter fabric treated in 8 hours

50,000 meter…………= (8 x 50,000)/14,400 = Approx 28 h