Balancing of machines for complete
process house :Part-6
Finishing (Softener application)
For finishing purpose stenter machine (4 chambers)
will be used and fabric will be given softening treatment.
Machine working speed: 40 m/min, M/c utilization=
80%
Total production per shift (8 hours or 480 min)=
(speed x utilization x 480)/100
= (40 x 80 x 480)/100 = 15,350 meter
Total fabric to be dyed= 50,000/-
15,350 meter fabric treated in 8 hours
50,000 meter…………= (8 x 50,000)/15,350 = Approx 26 h
Balancing of machines for complete
process house :Part-7
Finishing (Zero-Zero)
For this purpose one Sanforizing (zero-zero) is
needed to dimensionally stabilize cotton fabric.
Machine working speed: 40 m/min, M/c utilization=
80%
Total production per shift (8 hours or 480 min)=
(speed x utilization x 480)/100
= (40 x 80 x 480)/100 = 15,350 meter
Total fabric to be dyed= 50,000/-
15,350 meter fabric to be preshrunked in 8 hours
50,000 meter…………= (8 x 50,000)/15,350 = Approx 26 h